Yarn lead time is a stack of stages, not a single factory promise. Buyers who only ask “how many days for production?” miss sampling, lab dips, packaging print, booking, and ocean transit—then wonder why the warehouse date slipped. Plan the full path from brief to door, then negotiate the controllable middle.
This calendar is for wholesale / OEM knitting and crochet programs from China. Pair with MOQ explained and sample process. Program inquiry: bulk yarn supplier.
| Stage | Indicative range | Notes |
|---|---|---|
| Supplier shortlist & brief | 3–10 days | Your side + responses |
| Stock samples | 3–10 days + courier | Faster if styles exist |
| Custom / OEM development sample | 1–3 weeks | New count or blend |
| Lab dips (custom color) | 1–3 weeks including revisions | See lab dip guide |
| Bulk production (dye + wind + pack) | Often 3–6 weeks after approvals | Volume and color count matter |
| Private-label print / materials | +few days to +2 weeks | Artwork must be final |
| Inland + export docs + vessel | 1–2 weeks typical | Port congestion varies |
| Ocean transit | ~2–5+ weeks by lane | Plus destination clearance |
First bulk programs commonly land around 6–10 weeks from serious supplier selection to warehouse—longer if colors iterate or peak season hits.
Assume: existing acrylic style, 4 custom colors, retail ball pack, FOB Shanghai.
| Week | Milestone |
|---|---|
| 0 | Brief + style confirmation |
| 1 | Stock hand-feel sample approved |
| 2–3 | Lab dips submitted / revised / approved |
| 3 | PO issued; deposit / terms cleared; artwork locked |
| 4–7 | Bulk dye, winding, balling, packing |
| 7–8 | QC, docs, cargo to port, vessel load |
| 9–12 | Ocean + clearance + inbound (lane-dependent) |
Running stock colors can collapse weeks 2–3 and shorten bulk—often the right path for a first sellable test.
For Amazon inbound timing, also read Amazon FBA Yarn: Factory Direct vs Wholesale.
| Period | Planning tip |
|---|---|
| Pre–Chinese New Year | Book capacity early; expect rush then shutdown |
| CNY shutdown | Little or no production; courier delays |
| Post-CNY restart | Queues for dye houses and packing |
| Mid-year / Q4 retail peaks | Capacity tight on popular acrylics and chenille |
Ask your supplier for a written capacity note when your PO sits near holidays—not a verbal “should be fine.”
Ambiguous “ASAP” POs create disputes; dated milestones create accountability.
“25 days” often means bulk production after approvals. Sampling, dips, artwork, and freight sit outside that number.
Sometimes for capacity priority—not always for dye chemistry or ocean schedules. Ask what is actually compressible.
Usually yes for production, if inventory or running dye plans exist. Still confirm real availability for your kilo volume.
Send target warehouse or ex-factory date, color count, and kilos via Get Free Quote, and review bulk yarn program expectations.
Plan yarn lead time as a calendar of gates: brief → sample → color → PO → bulk → ship → clear. Negotiate the production block honestly, but protect the approval and freight buffers that determine when goods are actually sellable.
Next steps: Pick an in-warehouse date, build the backward calendar, and request a dated production plan with your style and color list.
Sullivans International plans sample-to-ship timelines for knitting and crochet yarn export programs. Get a free quote · Bulk yarn supplier · Browse yarn catalog.